Concerning the California Bearing Ratio Check



The California Bearing Ratio(CBR) take a look at can be a measure of resistance of a cloth to penetration of standard plunger under managed density and dampness situations. It was developed by the California Division of Highways to be a way of classifying and assessing soil- subgrade and foundation program products for adaptable pavements.

CBR test may very well be conducted in remoulded or undisturbed sample. Check includes triggering a cylindrical plunger of 50mm diameter to penetrate a pavement part content at 1.25mm/minute.

The masses for 2.5mm and 5mm are recorded. This load is expressed as being a share of normal load value in a respective deformation level to get CBR value.

California Bearing Ratio Take a look at on Subgrade Soil
The goal of this test could be the perseverance of California Bearing Ratio value of the subgrade soil.

Apparatus for CBR Take a look at
Loading equipment-any compression equipment can work at consistent price of 1.25mm for each minute can be employed. Cylindrical moulds- moulds of 150mm diameter and 175mm height presented with a collar of about 50mm length and removable perforated foundation.

Compaction rammer, surcharge weight-annular weights Each and every of 2.5kg and 147mm diameter. IS sieve 20mm, Coarse filter paper, equilibrium and so on.

Procedure of California Bearing Ratio Test
Sieve the sample through 20mm IS sieve. Take five kg of your sample of soil specimen. Add h2o to your soil in the quantity these that ideal humidity content material or discipline humidity material is reached.

Then soil and water are blended totally. Spacer disc is placed in excess of The bottom plate at The underside of mould plus a coarse filter paper is put above the spacer disc.


The organized soil water mix is divided into five. The mould is cleaned and oil is utilized. Then fill one particular fifth with the mould Using the prepared soil. That read more layer is compacted by providing 56 evenly dispersed blows employing a hammer of weight four.89kg.

The highest layer with the compacted soil is scratched. All over again 2nd layer is crammed and approach is repeated. Right after third layer, collar is also hooked up on the mould and method is ongoing.

Immediately after fifth layer collar is taken out and extra soil is struck off. Take out base plate and invert the mould. Then it is clamped to baseplate.

Surcharge weights of two.5kg is placed on leading surface of soil. Mould made up of specimen is placed in posture to the testing machine.

The penetration plunger is brought in connection with the soil and also a load of 4kg(seating load) is used to ensure Make contact with concerning soil and plunger is set up. Then dial readings are adjusted to zero.

Load is applied these kinds of that penetration level is one.25mm for each minute. Load at penetration of 0.five, 1, one.5, two, 2.five, three, 4, five, 7.5, ten and 12.5mm are observed.